No Anti-Profiteering Contravened in Post-GST Construction Projects
1. The Core Dispute: Alleged Profiteering on Post-GST Bookings
An applicant (homebuyer) who booked a flat in 2019 in the residential project ‘Urban-67A’, Gurugram, alleged that the developer failed to pass on the benefit of Input Tax Credit (ITC). The buyer contended that under Section 171, the developer was obligated to reduce the flat’s price to reflect the “additional” credit available under the GST regime.
Applicant’s Argument: Section 171 mandates a commensurate reduction in price whenever there is an increase in ITC benefit.
Developer’s Stand: The project started and the prices were fixed entirely in the post-GST era. Therefore, no “transitional” or “additional” benefit accrued that wasn’t already factored into the base price.
2. The Investigation Findings (DGAP Report)
The Director General of Anti-Profiteering (DGAP) conducted a detailed investigation and concluded that there was nil profiteering. The key findings were:
Wholly Post-GST Project: The project commenced in 2019, well after the rollout of GST in July 2017.
No Comparative Benefit: Anti-profiteering measures are designed to capture tax savings when a project “straddles” the pre-GST (VAT/Service Tax) and post-GST periods. For projects launched after July 2017, the builder sets the price based on the known post-GST cost structure, including available ITC.
ITC Ratio: The investigation found that the ITC-to-Turnover ratio did not show any windfall gain for the developer that would require a price reduction.
3. Legal Ruling: The “Post-GST” Principle
The Tribunal accepted the DGAP report, relying on judicial precedents (including the Delhi High Court judgment in Reckitt Benckiser).
I. Scope of Section 171
Section 171 is triggered only in two specific scenarios:
Reduction in Tax Rate: When the government lowers the GST rate on a supply.
Benefit of ITC: When more credit becomes available compared to the previous tax regime.
II. Exemption for Entirely Post-GST Supply
The court held that if both the construction and the supply (booking/payment) take place entirely after July 1, 2017, the provisions of Section 171 are generally not attracted. Since there is no “pre-GST” baseline to compare against, there is no “additional” benefit to be passed on.
4. Final Verdict
The Tribunal held that the developer had not contravened the law. The project was launched in a regime where the tax rules were already established, and the developer had validly exercised the option for GST rates (e.g., 5% or 1% without ITC for affordable housing).
Outcome: The proceedings against the developer were dropped.
Result: The applicant’s request for a price reduction was rejected.
Key Takeaways for Homebuyers & Developers
For Homebuyers: Be aware that “commensurate reduction” usually refers to the change in tax benefit. If you book a flat in a project that started in 2019 or later, you are unlikely to win a profiteering case based on “transitional” ITC.
For Developers: Maintain project-wise cost sheets and ITC records. The current judicial trend focuses on project-specific savings rather than broad mathematical ratios.
Sunset Clause: Note that the government has notified April 1, 2025, as the sunset date for new anti-profiteering complaints.
| 1. The project “Urban-67A” commenced entirely after implementation of GST; and |
| 2. The Respondent had validly exercised the option to adopt old GST rates under Notification No. 03/2019-Central Tax. |