Anti-Profiteering: No Liability for Post-GST Flat Bookings

By | March 2, 2026

Anti-Profiteering: No Liability for Post-GST Flat Bookings


Issue

Whether a real estate developer is liable for “profiteering” under Section 171 of the CGST Act if they do not reduce the price of a flat booked after the introduction of GST (post-July 1, 2017), even if they previously stated that Input Tax Credit (ITC) benefits would be passed on.


Facts

  • Project & Complaint: A home buyer in the project “Shriram Greenfield” (Bengaluru) alleged that the developer failed to pass on the benefit of additional ITC available under the GST regime.

  • Initial Report: The Director General of Anti-Profiteering (DGAP) initially calculated a profiteering amount of ₹14.48 crores against the developer, including a specific claim of ₹2,32,982 for the complainant.

  • Legal Shift: Following the Delhi High Court’s ruling in Reckitt Benckiser (2024), the Competition Commission of India (CCI) ordered a re-investigation in March 2024. The High Court had clarified that there is no “one-size-fits-all” mathematical formula for determining profiteering.

  • The “Post-GST” Factor: Upon re-investigation, it was confirmed that the complainant had booked the flat in the post-GST period.


Decision

The Authority (GSTAT/CCI) accepted the revised DGAP report and ruled in favor of the developer based on the following principles:

  1. Price Discovery: In a post-GST scenario, the sale price of a flat is determined after considering all available benefits, including the new ITC structure. Therefore, the benefit is essentially pre-factored into the market price offered to the buyer.

  2. No Saving Comparison: Since the booking happened after July 1, 2017, there was no “pre-GST price” to compare it against to determine if a “commensurate reduction” occurred.

  3. Ratio Analysis: The DGAP’s revised scrutiny showed that the ratio of ITC to purchase value actually decreased from 15.25% (pre-GST) to 14.57% (post-GST), meaning the developer had no additional savings to pass on.

  4. Contractual Promises vs. Legal Mandate: The complainant’s argument—that the builder had previously confirmed they would pass on ITC—was rejected. The Court held that a mere statement or confirmation does not create a legal right to a “benefit” if the statutory math under Section 171 does not actually show profiteering.


Key Takeaways for Taxpayers & Home Buyers

  • Booking Date is Decisive: Anti-profiteering measures are primarily “transitional.” They protect those who booked before GST and saw their tax structure change mid-way. For those buying after July 2017, the price is considered inclusive of all GST efficiencies.

  • Absence of Fixed Formula: Courts have rejected the use of rigid mathematical formulas by the DGAP. Every case must be evaluated based on actual cost escalations, market conditions, and tax ratios.

  • Sunset Clause: Note that the government has set April 1, 2025, as the sunset date for the anti-profiteering authority. Post this date, the market—not the tax authority—is expected to regulate pricing benefits.


GOODS AND SERVICE TAX APPELLATE AUTHORITY, NEW DELHI
DGAP
v.
Shrivision Towers (P.) Ltd.*
Mayank Kumar Jain, Judicial Member
NAPA/136/PB/2025
JANUARY  29, 2026
ORDER
1. The Karnataka State Screening Committee received a complaint made by Shri Rajiv Kumar Aggarwal resident of J-402, Rohan Vasantha, Varthur, Main Road, Marathahalli, Bengaluru, Karnatak, alleging profiteering against the respondent in respect of the flat D-206 in their project named “Shriram Greenfield” It was alleged that the respondent did not pass on the benefit of input tax credit to the complainant by way of commensurate reduction in the prices on purchase of said flat on introduction of GST w.e.f. 01.07.2017.
2. On the basis of above complaint, the matter was examined by the Standing Committee and the same was referred to the Director General of Anti-profiteering, hereinafter DGAP. Detailed investigation was conducted by the DGAP in the light of the observations made by Hon’ble High Court of Delhi in the Judgement in Reckitt Benckiser India (P.) Ltd. v. Union of India GSTL 344 (Delhi)/(2024) 14 Centax 374.
3. The Respondent provided some relevant documents for investigation to DGAP which are duly considered.
4. The DGAP, in its Report, mentioned that the project had two phases such as phase-I and phase-II respectively. Phase-I started in the month of March 2015 and got completed in August 2019 while Phase-II was started on 03.10.2017 and completed on 30.09.2021, the post-GST period, therefore, Phase-II was out of the purview of the investigation. The applicant/complainant has booked his flat in phase-I, in post GST period. The present investigation pertains to phase-I of the project.
5. During the investigation, the DGAP scrutinised the relevant documents submitted by the respondent and found that during the pre- GST period total purchase value of the inputs and services of the project “Shriram Greenfield phase-I” was Rs. 1,78,88,70,090 while in post – GST period the purchase value of the inputs and services was Rs. 1,36,55,05,946. During the Pre-GST period the respondent avail credit of Service Tax to the tune to Rs. 12,70,01,316. Credit of VAT availed was Rs. 14,58,21,139. During Pre-GST period ITC of GST availed by respondent was Rs. 19,89,66,636. The ratio of credit availed to purchase value as per pre- GST period was 15.25% while it was 14.57% was in post GST period. The ratio of ITC as a percentage of expenses incurred on purchase of inputs Goods and Services in the post GST period was reduced as against the percentage during pre-GST period. Therefore, there was no saving made by respondent on account of implementation of GST.
6. On the basis of the above finding, the DGAP arrived at the conclusion that the respondent did not contravene the provision under section 171 of the Central Goods and Service Tax, 2017.
7. Notice was issued to complainant Shri Rajiv Kumar Aggarwal. He filed his objections against the report of DGAP to the effect that; –
(a)That at the time of booking the respondent confirmed that the benefit of input tax credit would be passed to him.
(b)There is inconsistency in project definition. Earlier the DGAP identified the profiteering of approx. Rs 2.32 lakh but in the revised report the amount of profiteering reduced to zero.
(c)If the complainant was not entitled to any benefit of ITC since he booked the flat in January 2018, the builder would not have send a subsequent e-mail making a promise to pass benefit of ITC to him
(d)The home buyers are entitled for ITC benefit regardless to the fact that they booked flat before or after GST period
8. The respondent submitted its reply against the objection of the complainant that the condition mentioned in the mail that benefit of ITC could be passed to the customers was conditional. The allegation of inconsistency in treating both phases separately is factually incorrect and legally misconceived because the construction of Phase II was commenced entirely in post GST period.
9. Further it is stated that as per the paragraph 128 (d) of the Judgement passed by Hon’ble Delhi High Court in Reckitt Benckiser India Pvt. Ltd. (supra), the DGAP has excluded phase-II for determination of profiteering. The DGAP has correctly adopted the methodology during investigation. Since pre- GST, ITC to purchase ratio was 15.25% and post- GST ITC it was 14.57% therefore, ITC ratio got reduced in post- GST period. As a result of it no cost savings was made to the respondent.
10. The representative of the DGAP argued in support of the report submitted by DGAP.
11. I have heard learned representative of the DGAP and learned Chartered Accountants appeared on behalf of respondent. The complainant did not appear in spite of giving opportunity for personal hearing.
12. Perused the record.
13. The perusal of the record goes to show that earlier the DGAP had submitted its report calculating an amount 14,48,44,274 as profiteering against respondent and profiteering calculated in respect of the complainant was Rs. 2,32,982. The matter was pending before Competitive Commission of India, hereinafter CCI, the erstwhile authority. The CCI vide its letter dated 20.03.2024 directed the DGAP for re- investigation of this matter under rule 129 of the CGST Rules, 2017. As per the Judgement passed by Hon’ble High Court, Delhi, no fixed/ uniform method or mathematical formula can be laid down for determining profiteering. The Hon’ble High Court in para 128 of the Judgement, laid down certain guidelines for computation of profiteering.
14. The Hon’ble High Court Delhi in Reckitt Benckiser India Pvt. Ltd. (supra) in para 128 laid down certain guidelines for computation of profiteering such as; –
“128. There is no dispute with regard to the methodology to be adopted in the following four scenarios; –
(a)……
(b)……
(c)……
(d) If the flat is constructed in the post-Goods and Services Tax period and it is purchased after construction being complete by making upfront payment of the full price, no benefit of Input Tax Credit would be available as the price of the flat would have been fixed after taking into account the Input Tax Credit which has become available to the builder in the post-Goods and Services Tax period and which was not available to him in the pre-Goods and Services Tax.”
15. Admittedly, in the present matter the flat was booked by applicant in post-GST period. As per the Judgement of High Court of Delhi, since the price of the flat would have been fixed after taking into account the ITC which has become available to the builder in the post-GST period and which was not available to him in pre-GST period no benefit of ITC to home buyer would be available.
16. During the investigation the DGAP, after scrutinizing the relevant documents and considering the reply submitted by the respondent, arrived at the conclusion that the respondent has not contravened the provision under section 171 of the Central Goods and Services Act 2017. The DGAP has taken into consideration the ITC availed, and the purchase value of Goods and Services during pre and post GST period.
17. So far as the objection made by the complainant are concerned, I am of the view that merely by making a confirmation, that benefit of ITC would be passed, does not create any legal right to the applicant to claim benefit of the ITC. In view of the Judgment passed by Hon’ble High Court of Delhi, the DGAP submitted its revised report which is based on relevant data and documents.
18. In view of the above the objections raised by applicant does not carry any weight, therefore, they are liable to be rejected.
19. The report of the DGAP dated 03.02.2025 deserves to be accepted.
ORDER
20. The report of the DGAP dated 03.02.2025 is accepted.
21. The objections made by the complainant, against the report of the DGAP, are rejected.
22. Let the copy of the Judgement be communicated to concerned CGST/ SGST Commissionerate for record and necessary action, if any.
23. Judgement pronounced in open court today.
Category: GST

About CA Satbir Singh

Chartered Accountant having 12+ years of Experience in Taxation , Finance and GST related matters and can be reached at Email : Taxheal@gmail.com