Statutory GST Hikes Overrule Contracts; Recovery Paused Until Government Reimbursement is Secured.
The Dispute: Statutory Hikes vs. Fixed-Price Contracts
The Conflict: The petitioner had ongoing contracts with government entities executed prior to July 2022, when the GST rate was 12%. On July 18, 2022, Notification No. 03/2022-Central Tax (Rate) increased the rate to 18%.
The Department’s Demand: The Tax Department demanded the differential 6% tax for all supplies made after the effective date.
The Contractor’s Dilemma: The government departments (the clients) were still paying based on the old 12% rate, leaving the contractor with a massive unfunded tax liability.
The Judicial Verdict
The High Court ruled in favour of the Assessee regarding the timing of the recovery, while upholding the legality of the tax itself:
1. Statutory Rate Prevails Over Contracts
The Court clarified that GST is a statutory levy. Even if a contract says the rate is 12%, a government notification can prospectively increase it to 18%. Parties cannot “contract out” of a tax rate change. Therefore, the 18% rate is legally valid for all work done after July 18, 2022.
2. “Abeyance” of Recovery
In a significant move for the contractor’s cash flow, the Court ordered that the tax recovery be kept in abeyance (paused).
The Logic: Since the government departments (Respondents 6 to 8) are the ones who ultimately owe the tax to the contractor, the Tax Department should not recover it from the contractor until the client departments reimburse them.
3. Six-Month Deadline for Government Departments
The Court directed the relevant government departments to process and secure the reimbursement of the differential 6% GST within six months. Only after this reimbursement is “secured” can the Tax Department proceed with recovery against the contractor.
Key Takeaways for Government Contractors
Check the “Change in Law” Clause: Most government contracts have a “Change in Law” or “Taxes and Duties” clause. Use this judgment to argue that a GST notification is a statutory change that necessitates a contract price revision.
Abeyance as a Shield: If you are facing a demand for the 6% differential, you can seek a stay on recovery by proving that you have initiated reimbursement claims with your client (the Government Department).
Proof of Supply Date: The 18% rate only applies to supplies made after July 18, 2022. Ensure your measurement books (MB) and invoices clearly distinguish between work completed before and after this date.
Interest Liability: The Court noted that other undisputed demands must be paid with interest. Only the “differential tax” arising specifically from this rate change was granted the “abeyance” relief.
WMP Nos. 7654, 7655, 7660 & 7662 OF 2026
” 6.It is submitted that the current prevailing rate of 12% GST was calculated while preparing the estimate. Hence, the approval and fund for making payment for the 6% difference cost has to be obtained from the competent authority. Action has been taken by this respondent to settle the 6% differences cost. After attending various remarks and observations made by the higher officials, finally this respondent addressed a letter to the Superintending Engineer, National Highways, Salem in Lr.No. 678/2022/A1 dated 17.07.2023 to take necessary action to get the 6% of GST from the National Highways Authority of India for making payment to the Contractor. In turn, the Superintending Engineer, National Highways, Salem has addressed a letter in Lr.No.302/2023/A2 dated 10.08.2023 to the Chief Engineer, National Highways, Chennai recommending to get 6% difference of GST. It is submitted that necessary orders are being expected by this respondent and on receipt of necessary orders and funds, the difference of 6% GST will be settled to the contractor. It is submitted that following part payments with 12% GST have been made in respect of above work.
| S.No. | Month | Bill No. | Value of work done (Rs.) | 12% GST |
| 1 | August 2022 | I & Part | 8,42,86,022- | 1,01,14,323- |
| 2 | Sept 2022 | II & Part | 6,34,99,065- | 76,19,888- |
| 3 | Sept 2022 | III & Part | 4,79,19,870- | 57,50,384- |
| 4 | Nov 2022 | IV & Part | 3,88,36,525- | 46,60,503- |
| 5 | January 2023 | V & Part | 1,99,09,181- | 23,89,102- |
| 6 | March 2023 | VI & Part | 3,04,41,694- | 36,53,003- |
| 7 | June 2023 | VII & Part | 6,14,81,930 | 73,77,832 |
| Total | 34,63,74,287- | 4,15,65,035- |
7.It is pertinent to submit that the bill mentioned in May 2023 is not related to National Highways, Salem Division. It is also submitted that the bills mentioned in February 2023 & April 2023 were raised for different work for which 18% GST has been paid in July 2023.
8.It is submitted that on receipt of necessary funds and orders from the Competent Authority by Project Director, National Highways Authority of India, the petitioner will be settled the difference of 6% GST without any delay.”
