Real estate developers must pass on the 1.31% additional ITC benefit to homebuyers as a price reduction.
The Dispute: The Transition Windfall
The Conflict: When GST was introduced, the “cascading effect” of taxes (tax on tax) was reduced because developers could now claim ITC on almost all inputs (cement, steel, services) which were previously restricted or costly.
The Investigation: The DGAP compared two ratios:
Pre-GST: ITC as a percentage of expenses was 8.64%.
Post-GST: ITC as a percentage of expenses rose to 9.95%.
The Profiteering: This increase of 1.31% represented “savings” for the developer. Under Section 171, this benefit was mandatory to be passed on to buyers via a commensurate reduction in the base price of the flats.
The Judicial Verdict: Against the Developer
The Authority confirmed the profiteering amount of ₹1.21 crores based on the following:
1. Developer’s Admission
Significantly, the respondent (developer) accepted the DGAP’s methodology and expressed a willingness to refund the amount. This made the investigation’s findings conclusive.
2. Refund with Interest
The Authority ordered that the benefit must be returned to the homebuyers along with 18% interest. This interest is calculated from the date the extra amount was collected until the date it is actually refunded.
3. Penalty Immunity
The ruling provided a specific “window of grace”:
The Law: Penalty provisions under Section 171(3A) were only effective from January 1, 2020.
The Outcome: Since the developer agreed to the amount, no penalty would be levied if the profiteered amount was deposited/refunded within 30 days of the order.
Key Takeaways for Homebuyers & Developers
The 1.31% Benchmark: While each project is different, this ruling provides a benchmark for transition-era projects. If your project spanned the 2017 transition, a 1% to 3% price reduction is often legally due to you.
Commensurate Reduction: This does not mean a “discount.” It means the base price of the flat should be lowered so that the total “cum-tax” price reflects the tax savings.
Calculation Period: Note that the investigation covered a long duration (2017 to 2025). Anti-profiteering checks are not one-time events; they cover the entire construction cycle until the Completion Certificate (CC) is received.
Consumer Welfare Fund: If certain homebuyers cannot be traced, the developer cannot keep that money. Those unclaimed portions must be deposited into the Consumer Welfare Fund.
| a. | The DGAP conducted investigation for the period 01.07.2017 to 31.05.2025. |
| b. | The Respondent did not opt for scheme for discharging GST @ 5% (after 1/3rd abatement towards Land) in accordance with the Notification No. 3/2019- Central Tax (Rates) dated 29.03.2019 w.e.f. 01.04.2019. Therefore, the Respondent has to pay GST @ 12% with ITC w.e.f. 01.04.2019. Since the Respondent had not opted for the scheme of 5% GST without ITC w.e.f. 01.04.2019, therefore, the profiteering needs to be calculated upto the 31.05.2025 based on ITC availed. |
| c. | Before introduction of the GST, the Respondent was not eligible to avail credit of Service Tax and CENVAT credit of Central Excise duty in respect of the units for the project “Arvind Uplands I” sold by him. |
| d. | In post-GST regime, the Respondent was eligible to avail input tax credit of GST paid on all the inputs and input services as they had not opted new scheme as mentioned in Para 3(b) above, hence profiteering had to re-worked out in the instant investigation up to 31.05.2025. |
| e. | Out of total 180 villas, 89 Villas having area 23,989 Sq. Mts. were constructed, booked and handed over in the post-GST regime. That remaining 91 Villas (180-89) having area 23,271 Sq. Mts. were either constructed or booked in the pre-GST regime. Therefore, these 91 Villas having area 23,271 Sq. Mts. are covered in the present investigation. |
| f. | As per CA certified Annexure II submitted by the Respondent vide submission dated 20.10.2025, he has availed Input Tax Credit of GST for the period July, 2017 to 31.05.2025 to the tune of Rs. 13,79,45,097/-. Further, as per the CA certified Annexure IV submitted by the Respondent, they had reversed an amount of Rs. 5,60,77,652/- vide debit entry in their GSTR Returns for the FYs of 2019-20, 2020-21, 2021-22, 2022-23, 2023-24, 2024-25 and 2025-26 under Rule 42 & Others of the CGST Rules, 2017. In support of the said claim, the Respondent submitted copies of GSTR Returns for above said FYs and Electronic Credit Ledgers, which were found in order, therefore, the reversal has been accepted by the DGAP based on the CA certification. Accordingly, the Net ITC availed by the Respondent after reversal is Rs. 8,18,67,445/-. |
| g. | The calculation of profiteered amount from the data submitted by the Respondent has been worked out as tabulated in table-A below: – |
| S. No. | Particulars | Pre-GST Period | Post-GST Period |
| 1 | Purchase Value of Goods and Services (Excluding Taxes and Duties) | 42,28,25,4 94 | 82,28,13, 508 |
| 2 | Credit of Service Tax availed | 3,65,50,36 2 | |
| 3 | Credit of VAT availed | ||
| 4 | Total Credit Availed in Pre-GST Period | 3,65,50,36 2 | – |
| 5 | NetITC of GST Availed | 8,18,67,4 45 | |
| 6 | Ratio of Credit Availed to Purchase Value (in %) | 8.64 | 9.95 |
| Difference | 1.31 |
| h. | It is also observed that the Central Government, on the recommendation of the GST Council, had levied 18% GST (effective rate was 12% in view of 1/3rd abatement for land value) on construction service, vide Notification No. 11/2017-Central Tax (Rate) dated 28.06.2017. The effective GST rate was 12% for flats. Accordingly, based on the figures contained in table- ‘A’ above, the comparative figures of the ratio of input tax credit availed/available to the purchase value in the pre-GST and post-GST periods as well as the purchase value, the recalibrated base price and the excess realization (profiteering) during the post-GST period, are tabulated in Table-B below: – |
| Particulars | Post-GST | |
| Period | A | July’17 to 31.05.25 |
| Ratio of Credit availed to Purchase Value as per Table – A above (%) | B | 8.64/9.95 |
| Increase in input tax credit availed PostGST (%) | C | 1.31 |
| Purchase Value of Goods and Services (Excluding Taxes and Duties) during Post-GST Period | D | 82,28,13,508 |
| Total Savings on account of additional ITC benefit | E = D*C/100 | 1,07,78,857 |
| Total Saleable Area (in Sq. Ft.) as per list of buyers | F | 23,271 |
| Total Saving Per Sq. Ft. | G = E/F | 463.19 |
| Total Sold Area (in Sq. Ft.) | H | 23,271 |
| Base Profiteered Amount | I = G * H | 1,07,78,857 |
| i. | Whether the Respondent derived the benefit of additional input tax credit after the introduction of GST and if so, whether such benefit was passed on to the homebuyers in terms of Section 171 of the CGST Act or not? |
| ii. | Whether the Respondent is liable to refund the profiteered amount along with interest, if not passed on earlier? |
| iii. | Whether penalty under Section 171 (3A) of the CGST Act is attracted? |
