238 Villages Electrified Last Week Under Ddugjy

By | February 2, 2016
(Last Updated On: February 2, 2016)

238 Villages Electrified Last Week Under Ddugjy

238 villageshave been electrified across the country during last week (from 25th to 31stJanuary 2016) under Deen Dayal Upadhyaya Gram JyotiYojna (DDUGJY). Out of these electrified villages, 2 villages belong to Assam, 3 villages to Bihar, 40 to Jharkhand, 34 to Chhattisgarh, 143 in Odisha, 07 in Rajasthan, 3 in Tripura,5 in Uttar Pradesh and one village fall in the state of Madhya Pradesh. The progress of ongoing electrification process can be tracked on http://garv.gov.in/dashboard

An update on ongoing electrification process

In view of the Prime Minister, Shri Narendra Modi’s address to nation, on Independence Day, Government of India has decided to electrify remaining 18,452 unelectrified villages within 1000 days i.e. by 01st May, 2018.  The project has been taken on mission mode and strategy for electrification consists of squeezing the implementation schedule to 12 months and alsodividing village electrification process in 12 Stage milestones with defined timelines for monitoring.

During 2015-16, 4,781 villages have been electrified till date. Out of remaining 13,671 villages, 10,690 villages are to be electrified through grid, 1998 villages are to be electrified through off- grid where grid solutions are out of reach due to geographical barriers and 983 villages are to be electrified by State Govt own. Total 1654 villages were electrified during April 2015 to 14th Aug 2015 and after taking initiative by Government of India for taking it on mission mode, 3127 additional villages have been electrified from 15th August 2015 to 31st January.   In order to expedite the progress further, a close monitoring is being done through Gram Vidyut Abhiyanta (GVA) and various actions are also being taken on regular basis  likereviewing the progress on monthly basis during the RPM meeting, sharing of list of villages which are at the stage of under energisation with the state Discom, identifying the villages where milestone progress are delayed.

Source Ministry of Power 01-February, 2016

Leave a Reply

Your email address will not be published.