EPC Contract for ISRO Satellite Launch Vehicle is Works Contract , GST at applicable rate : Tamil Nadu AAR

By | March 12, 2020
(Last Updated On: March 12, 2020)

Tamil Nadu Authority of Advance Ruling

M/S Tata Projects Limited

1. Whether Supply of Engineering, Procurement & Construction (EPC) contract for establishment of Integrated Cryogenic Engine & Stage Test facility (ICET) where in both goods and services are supplied can be construed to be a Composite Supply in terms of Section 2(30) of CGST Act, 2017?
2. If Yes, Whether the Principal Supply in such case can be said to be “Establishment  of Fluids Servicing System (FSS)” can be taxable at 5% GST vide notification No. 45/2017-Central Tax (Rate) dt 14th November, 2017?
3. If Principal Supply taxable at 5%, whether the entire transaction in the contract is taxed as per the rate applicable to Principal Supply

TN/47/AAR/2019 dated 16.10.2019

Download Click here

Leave a Reply

Your email address will not be published.